Ordering Method
We have decided to go the safe route of ordering two boards for testing then 10 afterwards. We will loose roughly $298.75 by doing this, but the alternative is potentially loosing roughly $611.36.
Notes
- It takes roughly 15 days for a JLCPCB order to arrive.
PCB Deadlines:
-
March 8th: Inventory done.
-
March 10th: First version of Among Us and GPS boards get ordered.
-
March 25th: First version of boards arrive.
- Make changes to it before April 1st.
-
April 1st: Order second version of Among Us.
-
April 15th: Second version of boards arrive.
-
April 20th: Everything done, including hardware and code.
-
May 10th: Competition day.
CAD Deadlines
Standard avionics bays will have to be CADded.
Updated Plan for Development Workflow and Breakout Board Schedule
1. Project Outline Document
- Task: Create a comprehensive project outline document detailing the objectives, scope, and workflow for the breakout board development.
- Due Date: March 8, 2025
2. Development Workflow
- Breakout Board Design Process:
- Each breakout board design challenge will be completed by the development team in 1 week.
- After completion, a team meeting will be held to discuss and refine the design.
- One team member (rotated weekly) will finalize the design iteration based on the discussion.
- The finalized design will then be sent to JLCPCB for assembly.